Schon ab 30. Juni wird das Oktoberfest aufgebaut. Wir begleiten den Wiesnaufbau 2025 mit regelmäßig neuen Aufbaufotos.

In 2025, the construction of the Oktoberfest officially begins on June 30, and takes almost 12 weeks. More complex tent constructions, but in particular the lack of manpower, make the construction companies regularly push for longer set-up and dismantling times. Depending on the construction phase, up to 2000 people work on Theresienwiese.

As usual, we accompany the Oktoberfest construction with regular new photos from the construction site. You can find the galleries at the bottom of this page.

When does the Oktoberfest Construction begin in 2025?

The construction is separated into multiple phases to prevent separate construction sites from blocking each other. At the beginning of the construction, there are two lots, later only one. Lot 1 includes all big tents at the regular Oktoberfest, lot 2 is Oide Wiesn. This is this year's timetable:

June 30Big tents of the Oktoberfest and small tents on lot 1.
August 1stBig tents of the Oide Wiesn, Small tents on lots 1&2 as well as those outside
August 27Roller coasters, Ferris wheels, water rides, lot 1 is expanded to Bavariaring
September 3Bumper cars, ghost trains, flat rides, other attractions
September 8All other showmen businesses
September 11Stalls
September 12Stalls at the pillars (mostly almond stalls)
September 17Bread stalls