Over the ten weeks of the Oktoberfest construction 2018, we’ll provide you with regularly new photos.
The construction of the Oktoberfest 2018, its 185th edition, starts ten weeks before the beginning of the festival, which is July 16. Only the Schützen-Festzelt starts its construction one week early due to the restricted available space. This year, the main focus will be on the redecoration of the Schottenhamel-Festhalle and the Winzerer Fähndl. Depending on the construction phase, between 150 and 2000 workers work at the Theresienwiese.
Timetable
July 16 | Construction of the 16 large beer tents |
August 27 | Construction of the small beer tents and the municipal stands |
September 3 | Construction of the large rides |
September 10 | Construction of other rides |
September 13 | Marketers move into municipal and marketer-owned stands |
September 14 | Construction of the marketer-owned stands in the middle of the streets |
September 19 | Costruction of the bread stands |
September 22 | Beginning of Oktoberfest |